| Name
of Project |
Client |
Details |
NHAI Tamil Nadu VI C |
National Highways Authority of India |
4/6 Laning of a 40Km stretch between Trichy and Padalur on NH 45 on BOT basis. The Project involved construction of Major bridges across River Cauvery , Kollidam and Uppar. |
Design, Engineering, Finance, Construction, Operation and maintenance of the 4-lane Elevated Highway from Km 10.000 to
Km 14.000 and 6 lane access controlled highway from Km 14.000 to Km 29.500 on BOT basis (B'lore-Nelmanagala). |
National Highways Authority of India,
New Delhi |
6-lane access controlled highway from km 14.50 to km 29.50 with elevated 4-lane highway from km 10.15 to km 14.50, one flyover of length 348m, six over passes and all CD works. 4.35 km long elevated structure is supported on 1200mm dia RCC bored cast-in-situ pile foundations and piers. The super structure consists of Pre-cast segments of size 16.2m width with the external post tensioning are erected by using over head launching gantry. |
Extension of North Breakwater and construction of KPCL ware houses at Krishnapatnam port |
Krishnapatnam Port Company Limited, Hyderabad |
Construction of 3.6 Km long North & South Breakwater to protect the entrance channel and port |
Civil and Electro Mechanical EPC Package for Development of Krishnapatnam Port. (Phase-I) |
Krishnapatnam Port Company Limited, Hyderabad |
Berth length-1200m
No of vessels which can be berthed-6 Nos
Max Vessel Size-105,000 DWT
Draught at Berth-15.00m
Construction of 3.6 Km long North & South Breakwater to protect the entrance channel and port
Capital Dredging of over 26.0 million Cum including Sand trap to facilitate a navigable depth of 14.4 m
Four Nos. deep draught Berths / Terminals for Coal, Iron ore and General Cargo , designed for a ultimate depth of 19m below CD |
LSTK1-Sea Water Intake, Outfall and Product Water Conveyance System for CPCL, Chennai |
CPCL, Manali, Chennai-600 068 |
Sea Water intake and cross country piping system iclude caission well foundation including Diaphragm Walls, breast walls etc, Intake pump house and switch gear room, Approach Jetty, pipelines and other civil works along with all electromechanical works |
Bridge across River Godavari between
Yanam and Yedurlanka in East Godavari Dist.(A.P) on
BOT Basis |
Engineer-in-chief (R & B),(Admn.
& EAP), Govt. of A.P. Hyderabad. |
1.80 Km long high level bridge across
River Godavari with 9.40 KM long approaches Completed
Three months ahead of schedule |
Supply of Make-up Water System Turnkey
Package for Simhadri Thermal Power Project, Stage-1
for NTPC Visakhapatnam (2 x 500 MW) |
National Thermal Power Corporation,
New Delhi |
Complete makeup water system to supply
9000 Cum/Hr of seawater and 1500 Cum/Hrs sweet water
involvong Multi disciplinary engineering and construction |
Bridge across River Krishna between
Puligadda and Penumudi in A.P on B O T Basis |
Govt. of A.P. R& B, Dept. |
3.00 Km long High level Bridge across
River Krishna with 2.0 KM long Approaches.
Bridge work completed in less than a year. |
Construction of 17.30
Km long Nellore Bypass project on B O T (Annuity) Basis |
N.H.A.I. New Delhi |
Construction of 840 meters
long three lane twin bridge across River Pennar along
with minor bridges, Railway Over Bridge, Under passes
and other CD works
Completed three months ahead of schedule |